Client / Consortium IDRECO-INSUGMA
Category / Engineering and Design, Installation, Turn-key projects

Construction of an Flue Gas Desulphurization Plant(FGDP) of Units 5 and 6 at TPP Maritza East 2 JSC
Section 1: Construction of bypass gas ducts of Units 6. The Unit is entered in regular operation. Completed on 28.01.2011. New Unit 6 Bypass Gas Ducts have been constructed from ESPs to an existing stack with the erection of new flue gas fans.
Section 2: Construction of bypass gas ducts of Units 5. The completion deadline is 18.11.2011. New Unit 6 Bypass Gas Ducts have been constructed from ESPs to an existing stack with the erection of new flue gas fans.
Section 3: Construction of an essential FGDP. The following main facilities:
– Absorber, with wet stack, made of stainless steel. Wet stack to it of glass-reinforced plastic and a steel support structure of the wet stack. The height of the stack is 135 m.
– Pump houses I and II on which feeder and recycling pumps have been erected, and oxi-dation air compressors.
– Mill building with ball miles erected in it for drinding limestone into limestone suspension, and an automotive vehicle unloading station with an upstream crusher instalation and silos.

Final completion of the site: 2012